Jump to content

lot release and parallel QA testing


mlongval

Recommended Posts

Currently at our facility we are using a Rosys Plato for donor testing. When we receive new kit reagents we do a thorough visual inspection and a parallel QC test. Now the manufacturer is shipping componets instead of kits.

1. Should each lot of capture tray be tested?

2. Should each lot of indicatior cell be tested?

3. Should each lot of positive and negative control be tested?

Feedback would be apprecitated as to how you ensure QA of reagents received at your facility. email mlongval@partners.org or respond to this thread.

Thank you,

-Matt

Link to comment
Share on other sites

If the Rosys is anything like the ABS2000, you have to do QC with a new lot before you can use it anyway, so you will essentially be performing the parallel QC when you place the new lot on the instrument. If that is not the case, then you may want to have a policy to perform new QC when a new lot is placed on the instrument to cover your lot change.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
  • Advertisement

×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.